Skip to content Skip to sidebar Skip to footer

Case No. 466/9839/19 dated 19/02/2025

Here is the translation:

1. Subject of Dispute: Consumer rights protection in a case regarding non-commissioning of a multi-apartment residential building and recovery of penalty sanctions for delay.

2. Key Court Arguments:
– The court recognized that the developer cannot be forcibly compelled to commission the facility
– It was established that the defendant’s fault in delay is not proven due to objective reasons (prolonged land plot re-registration procedure, change of general contractor)
– Contracts provided for penalty sanctions for delay, but to recover them, the developer’s fault must be proven

3. Court Decision: Partially modified the reasoning part of previous court decisions, but essentially left unchanged – most of the plaintiff’s claims were denied.

Note: The court deviated from previous practice regarding interpretation of contract terms and establishing the developer’s fault.

Full text by link

E-mail
Password
Confirm Password
Lexcovery
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.