The essence of the resolution is to approve the procedure for using budget funds for the construction of main water pipelines in Mykolaiv Oblast due to the destruction of the Kakhovka Hydroelectric Power Plant. The document defines the mechanism for financing, reporting, and monitoring the use of funds from the state budget under budget program 3111840.
The document structure includes:
– Main resolution
– Procedure for using funds (13 points)
– Annexes with a list of construction objects and reporting form
– Amendments to the previous resolution No. 566 dated 06.06.2023
Key provisions:
1. The Recovery Agency is designated as the main fund administrator
2. Funds are directed to the construction of new main water pipelines to ensure water supply in Mykolaiv Oblast
3. A clear reporting mechanism is established – monthly reports from the funds recipient to the Recovery Agency (by the 10th) and from the Agency to the Ministry of Finance (by the 15th)
4. Specific construction objects are defined with funding volumes and commissioning deadlines by June 6, 2025
5. Monitoring of targeted fund use and regular reporting are provided for