Case No. 914/3208/23 dated 11/02/2025

Here is the translation:

1. Subject of Dispute: Invalidation of the electricity supply agreement by a universal service provider between LLC “Lvivenerhozbut” and LLC “SU-27”.

2. Key Court Arguments:
– The contract was concluded based on the distribution system operator’s data about the universal service consumer
– The respondent actually consumed electricity and made payments
– The court believes that the plaintiff did not prove grounds for declaring the contract invalid
– It is necessary to thoroughly establish the circumstances of contract conclusion and its compliance with legislation

3. Court Decision: Revoke the appellate court resolution and refer the case for new consideration to the appellate commercial court for additional examination of case circumstances.

Note: The court deviates from previous practice of considering similar disputes, requiring a more detailed analysis of all contract conclusion circumstances.

Full text by link

E-mail
Password
Confirm Password
Lexcovery
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.