The resolution introduces a two-year experimental project for the restoration of hydropower facilities of PJSC ‘Ukrhydroenergo’ damaged as a result of Russian aggression. The project is aimed at optimizing the timelines for restoring critical infrastructure to ensure the stable operation of Ukraine’s energy system. The document consists of two parts: the resolution itself (4 points) and the Project Implementation Procedure (11 points). The resolution defines the general principles, timelines, and sources of funding. The Procedure details the restoration process and defines the project participants and their powers.
Key project features:
– Simultaneous performance of design and survey and construction works is allowed
– Works can be carried out before project documentation approval based on technical solutions
– Several permit procedures have been canceled (urban planning conditions, archaeological research, project expertise)
– The procedure for commissioning objects has been simplified
– The Ministry of Energy is designated as the project coordinator, PJSC ‘Ukrhydroenergo’ as the customer, and PJSC ‘Ukrhydroproject’ as the general designer