This resolution establishes an experimental procedure for the construction and protection of critical infrastructure facilities in the fuel and energy sector of Ukraine. The project is aimed at the fastest possible execution of works to ensure the vital activity of the population under martial law.
The document structure includes:
– The main resolution launching an experimental project for 2 years
– Project implementation procedure with detailed description of procedures
– List of Cabinet of Ministers resolutions that are not applicable during project implementation
Key provisions:
1. During martial law, construction and protection of facilities are carried out without standard permit procedures (urban planning documentation, land allocation, etc.)
2. Project coordinators are the Ministry of Development and the Recovery Agency
3. Work customers can be infrastructure recovery services, military administrations, and the Recovery Agency
4. Advance payment for works up to 6 months is allowed
5. Simplified procedure for commissioning facilities based on a readiness certificate
– the document concerns critical infrastructure under martial law.